Lee County permitting: how a building permit package actually moves

By David Gizys · Founder & President
Updated September 1, 2026 · 7 min read
Which department actually has your permit
A Fort Myers mailing address does not mean the City of Fort Myers issues your permit. Six municipalities inside Lee County run their own building departments — Cape Coral, Fort Myers, Bonita Springs, Estero, Fort Myers Beach, and Sanibel — and everything outside their limits is unincorporated county work.
Unincorporated work goes to the Lee County Department of Community Development on Monroe Street in Fort Myers. One department, two arms you deal with separately: building and permitting services, which issues the building permit, and development services, which handles site work, subdivisions, and vegetation. On anything commercial or multifamily, both have to be satisfied, and they do not run on the same clock.
So the first move on a Lee County project is confirming jurisdiction against the parcel, not the address. It takes minutes. Getting it wrong costs an entire intake cycle and, on a tight lot, the design assumptions that came with the wrong code.
What eConnect gives you, and what it doesn't
Lee County runs permitting through eConnect, its Accela-based portal. Applications, plan uploads, review status, fee payment, and inspection scheduling all live there, and the county's guides describe electronic submittal as the standard path — paper submittal means collated plan sets delivered in person to the building department.
Contractors have to register for an eConnect account and get a signed user agreement on file with the department before they can file anything. Do that when you take the job, not the morning the package is ready. An unregistered account is a strange thing to lose a week to, and builders lose a week to it.
What the portal does not do is tell you anything. Corrections land back on the record and sit there until somebody logs in and looks. A package can wait a week on a two-line response while everyone on the job assumes the county is still reviewing it — and that lost week is entirely on the applicant's side of the fence.
How a Lee County submittal actually runs
Five stages, and the expensive mistakes almost all happen in the first two.
- 1Jurisdiction and zoning verification
Confirm the parcel is unincorporated, then confirm what the Land Development Code allows on it — use, setbacks, height, coverage, flood zone. This is design input, not paperwork, and it is cheapest before the plans are drawn.
- 2Development order, where one applies
Commercial, industrial, multifamily, and subdivision projects need a development order from development services before site work starts and before the building permit issues. On those projects the building permit is the second approval, not the first.
- 3Intake and the completeness screen
The package is first checked for completeness — required documents attached, signatures and seals present. An incomplete package is not forwarded to a reviewer, so it is not in line. It is in your inbox.
- 4Plan review and corrections
A complete package goes out to the reviewing disciplines the scope calls for. Comments come back on the portal record, you resubmit, and the file goes back around. Every round is a cycle, which is why the goal is a package that draws no comments rather than fast replies to the ones it draws.
- 5Issuance, fees, then inspections
Permit fees and impact fees come due at issuance, not at application. After that you are into inspections, and on a development-order site, a certificate of compliance before anyone gets a certificate of occupancy.
Development services issues development orders for site work on commercial, industrial, multifamily, and subdivision projects in unincorporated Lee County, and one has to be in hand before site work begins and before a building permit is issued. Closing out is its own step: before a site can be used as approved — including issuance of a certificate of occupancy — development services has to issue a certificate of compliance, which runs on a site inspection involving development services, Lee County Utilities, and the county and state transportation departments where work touches their right-of-way. Schedule both bookends at the front of the job.
You cannot clear the lot while you wait
Vegetation removal in unincorporated Lee County is its own permit through development services, in several flavors depending on the work — a notice of clearing, clearing for a single-family lot, a single tree, or clearing for soil borings and wells. The Land Development Code protects native vegetation; the permit establishes what you are allowed to take down.
Builders get burned here because clearing feels like site prep rather than permitted work, and a machine is cheap to keep busy while the permit is in review. Answer the clearing question during due diligence, when it is a line item, instead of after a neighbor calls it in, when it is an enforcement file.
What Lee County reviewers send back
Most rejections are not code arguments. They are a missing sheet or a missing form.
- Wrong jurisdiction — Filed with the county on a parcel inside a municipality, or the reverse. Nothing about the package is wrong except where it went.
- Incomplete at intake — A missing seal, an unsigned application, a conditional document nobody attached. It never reaches a reviewer, so the clock never starts.
- No site fill and grading plan — Lee County wants the grading plan with the application and wants it consistent with the Land Development Code. It is not a formality sheet.
- Thin flood documentation — Flood zone, base flood elevation, and the elevation data behind the proposed finished floor. On a coastal parcel this is the review, not a section of it.
- Missing private provider forms — Using a private provider means the compliance affidavit and the notice to the building official go in with the application, not after it.
- Owner-builder paperwork — When the owner is the applicant, the disclosure statement is part of the package. Its absence stalls intake the same way a missing seal does.
Flood is the variable that changes the project, not the package
On a parcel that already has a structure on it, the question that moves the numbers is substantial improvement. If the cost of the work equals or exceeds 50 percent of the market value of the building before it starts, the whole structure has to be brought into compliance with current flood requirements — which on a slab-on-grade house in an A or V zone usually means elevating it.
Two Lee County specifics matter. The county counts improvements cumulatively over a five-year window rather than judging each permit on its own, so a run of modest permits can trip a threshold no single one of them would. And market value comes from the property appraiser's assessment of the structure, or an independent appraisal by a Florida-licensed appraiser — not from what you paid, and not from the land.
Substantial damage works the same way from the other direction: if restoring a damaged building to its pre-damage condition would cost 50 percent or more of its market value, the repairs are treated as substantial improvement no matter what the scope of work says. Either way the answer drives an elevation certificate and a very different budget, which is why it belongs in site feasibility rather than in plan review.
How long the county actually has
Florida sets the outer limits, not the county. Section 553.792, Florida Statutes gives a local government 10 days to tell an applicant what is missing before the application is deemed properly completed, and 45 days after a completed application to specify what else it needs for sufficiency.
From there the decision deadlines depend on what you filed: 30 business days for a residential structure under 7,500 square feet, and 60 business days for multifamily up to 50 units, site plan approvals, subdivision plats, and lot grading and site alteration. Blow a deadline and the statute cuts the permit fee by 10 percent for every business day late, with the usual carve-outs for delay the applicant caused or timelines the applicant waived in writing.
Read that clock carefully, because it starts on a complete and sufficient application. Lee County's own residential permitting guide describes plan review typically running about 10 to 15 business days once a package is in review — but time spent incomplete at intake, or sitting on a correction nobody opened, is time nobody counts. The statutory clock is not your schedule. Your intake quality is.
Where the schedule is actually won
Florida lets an owner or contractor hire a licensed private provider to perform plan review and inspections instead of waiting on the jurisdiction's queue, and Lee County's permitting guides carry the forms for it. We price that work flat at $1 per square foot — $3,000 on a 3,000 square foot home — which is often the difference between a schedule you control and one the queue controls.
The other lever is the money at issuance. Impact fees come due when the permit is issued, which is late in the job to discover a number, and they are worth checking rather than paying on sight. On one project, that check saved $3,000.
The rest is ordinary permit management discipline. We typically take a project from intake to submission in about a week, where an in-house coordinator takes three to four, and we watch the portal so a correction never sits over a weekend. Some of it cannot be sped up and we do not pretend otherwise — the county's queue takes as long as it takes. What we control is that the package goes in permit-ready.
Frequently asked questions
- My address says Fort Myers. Do I file with the city or the county?
- Check the parcel, not the mailing address. The Lee County Department of Community Development permits unincorporated areas only; Cape Coral, Fort Myers, Bonita Springs, Estero, Fort Myers Beach, and Sanibel each run their own building department. Plenty of addresses that read "Fort Myers" are unincorporated county, so confirm jurisdiction on the parcel before anyone builds a submittal package.
- What is eConnect and do I have to use it?
- eConnect is Lee County's Accela-based permitting portal, and it is where unincorporated applications, plan uploads, fees, review status, and inspection scheduling live. Contractors register for an account and file a signed user agreement with the department before they can submit. Electronic submittal is the standard path; paper submittal means collated plan sets delivered in person.
- Do I need a development order before my building permit?
- On commercial, industrial, multifamily, and subdivision projects in unincorporated Lee County, yes. Development services issues the development order for site work, and it has to be in place before site work starts and before the building permit is issued. Single-family work on an existing lot generally does not need one, but the site fill and grading plan still goes in with the application.
- How long does Lee County have to review a building permit application?
- Section 553.792, Florida Statutes sets the limits: 10 days to identify what is needed to complete the application, 45 days after a completed application to request what is needed for sufficiency, then 30 business days to decide a residential structure under 7,500 square feet, or 60 business days for multifamily up to 50 units, site plan approvals, subdivision plats, and lot grading. A missed deadline reduces the permit fee by 10 percent per business day, unless the delay was the applicant's or the timeline was waived in writing.
- How do I know whether the 50 percent rule applies to my project?
- Compare the cost of the work to the market value of the structure before the work starts — the property appraiser's assessment of the building, or an independent appraisal by a Florida-licensed appraiser, not the land or the purchase price. Lee County counts improvements cumulatively over a five-year period, so several smaller permits can add up to substantial improvement. If it trips, the building has to meet current flood requirements, which is an elevation certificate conversation and usually an elevation one.
- Can I use a private provider in Lee County?
- Yes. Florida law lets an owner or contractor retain a licensed private provider for plan review and inspections, and Lee County's permitting guides include the compliance affidavit and the notice to the building official. Both forms go in with the application rather than after it. We run private provider inspections at a flat $1 per square foot.