Lee County permitting: how a building permit package actually moves

David Gizys, Founder & President of Development & Growth

By David Gizys · Founder & President

Updated September 1, 2026 · 7 min read

Which department actually has your permit

What eConnect gives you, and what it doesn't

How a Lee County submittal actually runs

Five stages, and the expensive mistakes almost all happen in the first two.

  1. 1
    Jurisdiction and zoning verification

    Confirm the parcel is unincorporated, then confirm what the Land Development Code allows on it — use, setbacks, height, coverage, flood zone. This is design input, not paperwork, and it is cheapest before the plans are drawn.

  2. 2
    Development order, where one applies

    Commercial, industrial, multifamily, and subdivision projects need a development order from development services before site work starts and before the building permit issues. On those projects the building permit is the second approval, not the first.

  3. 3
    Intake and the completeness screen

    The package is first checked for completeness — required documents attached, signatures and seals present. An incomplete package is not forwarded to a reviewer, so it is not in line. It is in your inbox.

  4. 4
    Plan review and corrections

    A complete package goes out to the reviewing disciplines the scope calls for. Comments come back on the portal record, you resubmit, and the file goes back around. Every round is a cycle, which is why the goal is a package that draws no comments rather than fast replies to the ones it draws.

  5. 5
    Issuance, fees, then inspections

    Permit fees and impact fees come due at issuance, not at application. After that you are into inspections, and on a development-order site, a certificate of compliance before anyone gets a certificate of occupancy.

The building permit is not the site work permit

Development services issues development orders for site work on commercial, industrial, multifamily, and subdivision projects in unincorporated Lee County, and one has to be in hand before site work begins and before a building permit is issued. Closing out is its own step: before a site can be used as approved — including issuance of a certificate of occupancy — development services has to issue a certificate of compliance, which runs on a site inspection involving development services, Lee County Utilities, and the county and state transportation departments where work touches their right-of-way. Schedule both bookends at the front of the job.

You cannot clear the lot while you wait

What Lee County reviewers send back

Most rejections are not code arguments. They are a missing sheet or a missing form.

  • Wrong jurisdiction — Filed with the county on a parcel inside a municipality, or the reverse. Nothing about the package is wrong except where it went.
  • Incomplete at intake — A missing seal, an unsigned application, a conditional document nobody attached. It never reaches a reviewer, so the clock never starts.
  • No site fill and grading plan — Lee County wants the grading plan with the application and wants it consistent with the Land Development Code. It is not a formality sheet.
  • Thin flood documentation — Flood zone, base flood elevation, and the elevation data behind the proposed finished floor. On a coastal parcel this is the review, not a section of it.
  • Missing private provider forms — Using a private provider means the compliance affidavit and the notice to the building official go in with the application, not after it.
  • Owner-builder paperwork — When the owner is the applicant, the disclosure statement is part of the package. Its absence stalls intake the same way a missing seal does.

Flood is the variable that changes the project, not the package

How long the county actually has

Where the schedule is actually won

Frequently asked questions

My address says Fort Myers. Do I file with the city or the county?
Check the parcel, not the mailing address. The Lee County Department of Community Development permits unincorporated areas only; Cape Coral, Fort Myers, Bonita Springs, Estero, Fort Myers Beach, and Sanibel each run their own building department. Plenty of addresses that read "Fort Myers" are unincorporated county, so confirm jurisdiction on the parcel before anyone builds a submittal package.
What is eConnect and do I have to use it?
eConnect is Lee County's Accela-based permitting portal, and it is where unincorporated applications, plan uploads, fees, review status, and inspection scheduling live. Contractors register for an account and file a signed user agreement with the department before they can submit. Electronic submittal is the standard path; paper submittal means collated plan sets delivered in person.
Do I need a development order before my building permit?
On commercial, industrial, multifamily, and subdivision projects in unincorporated Lee County, yes. Development services issues the development order for site work, and it has to be in place before site work starts and before the building permit is issued. Single-family work on an existing lot generally does not need one, but the site fill and grading plan still goes in with the application.
How long does Lee County have to review a building permit application?
Section 553.792, Florida Statutes sets the limits: 10 days to identify what is needed to complete the application, 45 days after a completed application to request what is needed for sufficiency, then 30 business days to decide a residential structure under 7,500 square feet, or 60 business days for multifamily up to 50 units, site plan approvals, subdivision plats, and lot grading. A missed deadline reduces the permit fee by 10 percent per business day, unless the delay was the applicant's or the timeline was waived in writing.
How do I know whether the 50 percent rule applies to my project?
Compare the cost of the work to the market value of the structure before the work starts — the property appraiser's assessment of the building, or an independent appraisal by a Florida-licensed appraiser, not the land or the purchase price. Lee County counts improvements cumulatively over a five-year period, so several smaller permits can add up to substantial improvement. If it trips, the building has to meet current flood requirements, which is an elevation certificate conversation and usually an elevation one.
Can I use a private provider in Lee County?
Yes. Florida law lets an owner or contractor retain a licensed private provider for plan review and inspections, and Lee County's permitting guides include the compliance affidavit and the notice to the building official. Both forms go in with the application rather than after it. We run private provider inspections at a flat $1 per square foot.
5.0/5· 3 reviews
~1 weekintake to submission
Hundreds / yrpermits managed
A decade+ working Florida countiesLicensed private-provider partner (PE)Coastal & flood-zone specialists
“Permit-ready in a week instead of a month. David caught two tabulation errors before submission that would have bounced us. Worth every dollar.”— Custom Home Builder, Anna Maria Island

This is part of our Permit Management & Project Coordination service. Tell us about your project and we’ll handle it end to end.

Ready to get permit-ready?

Tell us about your project. We reply within one business day — and we’ll tell you straight whether we’re the right fit.