Miami-Dade plans tracking: how to follow your plan review and what to do when it stalls

David Gizys, Founder & President of Development & Growth

By David Gizys · Founder & President

Updated October 26, 2026 · 6 min read

Look it up by process number, not permit number

Check which jurisdiction actually has your plans

How a Miami-Dade submittal moves

This sequence follows the county's published description of its process.

  1. 1
    Application and documents are accepted

    The county assigns your process number. Write it on everything; every later step keys off it.

  2. 2
    Upfront fees are paid

    Fees go in through the Pay Fees Due section using the process number. Plan review does not start until they are paid.

  3. 3
    Departments review at the same time

    Reviews run electronically and simultaneously across the departments your permit touches, so the slowest discipline sets the pace.

  4. 4
    The county notifies you

    You hear back through the contact methods on the application, either approved or needing corrections. A stale email address on the application is a schedule risk.

  5. 5
    Corrections go back in

    Reworks are reviewed on a timeline similar to the first pass, so every round costs real calendar time.

Who reviews your plans

The county's page names these reviews. Which ones apply depends on the project.

  • Building, structural, electrical, mechanical, plumbing. — Residential and commercial building review, with optional structural peer review.
  • Zoning plan review. — The county lists zoning plan review as its own step, separate from building review.
  • Environmental plan review. — Also listed separately, so expect its own reviewer and its own comments.
  • Fire Rescue and Water & Sewer. — Named as separate reviews on the county's page.
  • Public Works. — Handled through the Public Works Online Permit System, not the same portal.
The clock may not have started

The county says plan review begins after upfront fees are paid. It also says in-person paper submittals are converted to electronic format for a fee, which can add review time. If your portal shows nothing moving, check whether fees were paid before you assume a reviewer is sitting on the file.

Where the schedule actually slips

Tracking is not the same as inspections

Where we fit

Frequently asked questions

What is a process number in Miami-Dade?
It is the number the county assigns once your application and documents are accepted. You use it to pay upfront fees and to check plan review status in the Plans Status & Application Submittal Portal.
How long does Miami-Dade plan review take?
The county says initial reviews take about 24 hours to 10 business days depending on permit type and complexity, with reworks taking a similar time. Complex commercial or multi-department permits can run longer, and no one can promise a date.
Does the Miami-Dade portal show City of Miami permits?
No. The City of Miami runs its own tracking through iBuild and ProjectDox. Other municipalities in the county may run their own systems as well, so confirm the jurisdiction on the parcel first.
Can I track inspections in the same place as plan review?
No. The county describes a separate Schedule/Cancel/Track Inspections system for inspections, distinct from the plans status portal.
5.0/5· 3 reviews
~1 weekintake to submission
Hundreds / yrpermits managed
A decade+ working Florida countiesLicensed private-provider partner (PE)Coastal & flood-zone specialists
“Permit-ready in a week instead of a month. David caught two tabulation errors before submission that would have bounced us. Worth every dollar.”— Custom Home Builder, Anna Maria Island

This is part of our Permit Tracking & Status service. Tell us about your project and we’ll handle it end to end.

Ready to get permit-ready?

Tell us about your project. We reply within one business day — and we’ll tell you straight whether we’re the right fit.